Professional Scrum Master I PSM I · Free Practice Question Easy
Question 78
As self-managing professionals, which of the following do Developers manage?
(choose the best answer)
- A The Product Backlog.
- B The release plan.
- C The stakeholders invited to the Sprint Review.
- D The Sprint Backlog.
Reveal correct answer
Correct answer: D
Explanation
Developers in a Scrum Team are responsible for managing the Sprint Backlog. They collaborate to select and plan the work items from the Product Backlog for the upcoming Sprint. Once the Sprint begins, they self-manage to determine how to accomplish the work and create a plan to achieve the Sprint Goal. The Developers are accountable for tracking the work progress during the Sprint and making necessary adjustments to ensure timely completion. They work together to ensure transparency and collaboration in managing and delivering the Sprint Backlog. Ultimately, the Developers have the autonomy and authority to make decisions related to the Sprint Backlog and the implementation of the work.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.