Professional Scrum Master I PSM I · Free Practice Question Easy
Question 75
According to Scrum, when must a valuable and useful increment be made available?
(choose the best answer)
- A At the conclusion of each Sprint
- B Every other Sprint
- C During the Release Sprint
- D After approval by the Quality team
- E Upon request from the Product Owner
Reveal correct answer
Correct answer: A
Explanation
For the purpose of transparency, Scrum states that a valuable and useful increment must be available at the end of every Sprint. The increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints. It must be usable and meet the Definition of Done, regardless of whether the Scrum Team decides to release it.Discussion