Professional Scrum Master I PSM I · Free Practice Question Medium
Question 74
Which of the following are timeboxed events in Scrum?
(choose the best three answers)
- A Sprint Planning.
- B Daily Scrum.
- C Sprint Retrospective.
- D Sprint Testing.
- E Release Planning.
- F Release Retrospective.
- G Sprint 0.
Reveal correct answers
Correct answers: A, B, C
Explanation
In Scrum, there are 5 timeboxed events: Sprint, Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. These events have a maximum duration and are designed to provide structure and regularity to the Scrum Team's work.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.