Professional Scrum Master I PSM I · Free Practice Question Medium

Question 74

Which of the following are timeboxed events in Scrum?

(choose the best three answers)

  • A Sprint Planning.
  • B Daily Scrum.
  • C Sprint Retrospective.
  • D Sprint Testing.
  • E Release Planning.
  • F Release Retrospective.
  • G Sprint 0.
Reveal correct answers

Correct answers: A, B, C

Explanation

In Scrum, there are 5 timeboxed events: Sprint, Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. These events have a maximum duration and are designed to provide structure and regularity to the Scrum Team's work.