Professional Scrum Master I PSM I · Free Practice Question Easy

Question 54

Who is accountable for developing and explicitly communicating the Product Goal?

(choose the best answer)

  • A The Project Manager
  • B The Developers
  • C The Scrum Master
  • D The Product Owner
  • E The Product Manager
Reveal correct answer

Correct answer: D

Explanation

The Product Owner is accountable for effective Product Backlog management, which includes Developing and explicitly communicating the Product Goal.