Professional Scrum Master I PSM I · Free Practice Question Easy
Question 54
Who is accountable for developing and explicitly communicating the Product Goal?
(choose the best answer)
- A The Project Manager
- B The Developers
- C The Scrum Master
- D The Product Owner
- E The Product Manager
Reveal correct answer
Correct answer: D
Explanation
The Product Owner is accountable for effective Product Backlog management, which includes Developing and explicitly communicating the Product Goal.Discussion