Professional Scrum Master I PSM I · Free Practice Question Easy

Question 53

Who is accountable for tracking the progress towards the Sprint Goal?

(choose the best answer)

  • A The Scrum Master.
  • B The Developers.
  • C The Project Manager.
  • D The Product Owner.
Reveal correct answer

Correct answer: B

Explanation

According to the Scrum Guide, the Developers are responsible for tracking their progress towards the Sprint Goal. This includes managing the Sprint Backlog and updating it daily to reflect the remaining work. While the Scrum Master, Product Owner, and other stakeholders may provide support and guidance, ultimately, it is up to the Developers to manage their own work and ensure that they are on track to achieve the Sprint Goal.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need