Question 53
Who is accountable for tracking the progress towards the Sprint Goal?
(choose the best answer)
- A The Scrum Master.
- B The Developers.
- C The Project Manager.
- D The Product Owner.
Reveal correct answer
Correct answer: B
Explanation
According to the Scrum Guide, the Developers are responsible for tracking their progress towards the Sprint Goal. This includes managing the Sprint Backlog and updating it daily to reflect the remaining work. While the Scrum Master, Product Owner, and other stakeholders may provide support and guidance, ultimately, it is up to the Developers to manage their own work and ensure that they are on track to achieve the Sprint Goal.Discussion