True or False: The Scrum Master is primarily responsible for ensuring that enough Product Backlog items are selected at the Sprint Planning event in order to satisfy the stakeholders.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
The primary responsibility for ensuring that enough Product Backlog items are selected at the Sprint Planning event lies with the entire Scrum Team, not just the Scrum Master. This selection process should be a collaborative effort involving the Product Owner, the Developers, and the Scrum Master. While the Scrum Master does have a role in facilitating Scrum events and helping the team understand Scrum practices, the selection of Product Backlog items is more directly related to the Product Owner's accountability of managing the Product Backlog, and the Developers' role of selecting the Product Backlog items during Sprint Planning. However, it is worth noting that all members of the Scrum Team should collaborate to ensure that the items selected align with the Product Goal and Sprint Goal, and are feasible for the upcoming Sprint.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.