True or False: An organization that adopts Scrum should use the same terminology as defined in the Scrum Guide to avoid ambiguity and promote transparency.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: A
Explanation
According to the Scrum Guide, Scrum is a framework with specific roles, events, artifacts and rules. Changing the terminology of Scrum may cause confusion, misunderstanding and resistance to change. The new vocabulary of Scrum is a reminder that Scrum is different from the previous way of working and requires a shift in mindset and behavior. Management may feel less anxious by using familiar terms, but this may also prevent them from fully embracing Scrum and its benefits.Discussion