True or False: Scrum requires delivering a Done Increment at the end of each Sprint.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: A

Explanation

The Scrum Guide defines the Increment as a "concrete stepping stone toward the Product Goal" and emphasizes the importance of delivering a Done Increment at the end of every Sprint. The Increment should be in a usable condition and meet the Definition of Done as agreed upon by the Scrum Team. This enables the Scrum Team to receive feedback, gather insights, and adapt the product as necessary.