True or False: On big projects, It is good to have at least two Product Owners.
(Select the best answer)
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
If Scrum Teams become too large, they should consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product. Therefore, they should share the same Product Goal, Product Backlog, and Product Owner.Discussion