Question 13

Choose the statement that best describes the Product Backlog:

(choose the best answer)

  • A The Product Backlog is useful for producing the project plan.
  • B The Product Backlog does not get complete and is easily updated.
  • C The Product Backlog makes all available data that allows Developers to create a product. It is a list of requirements approved by the product manager.
  • D The Product Backlog is full of recognized tasks by the Developers. It contains many user stories.
Reveal correct answer

Correct answer: B

Explanation

There is no project plan in Scrum. The Product Backlog is an ordered list of everything known to be needed in the product. It is the single source of requirements for any changes to the product.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need