Professional Scrum Master I PSM I · Free Practice Question Medium
Question 13
Choose the statement that best describes the Product Backlog:
(choose the best answer)
- A The Product Backlog is useful for producing the project plan.
- B The Product Backlog does not get complete and is easily updated.
- C The Product Backlog makes all available data that allows Developers to create a product. It is a list of requirements approved by the product manager.
- D The Product Backlog is full of recognized tasks by the Developers. It contains many user stories.
Reveal correct answer
Correct answer: B
Explanation
There is no project plan in Scrum. The Product Backlog is an ordered list of everything known to be needed in the product. It is the single source of requirements for any changes to the product.Discussion