Professional Scrum Master I PSM I · Free Practice Question Easy

Question 12

Who is responsible for starting the Daily Scrum?

(choose the best answer)

  • A The Scrum Master, to make sure the event happens and stays within the timebox.
  • B The person who arrives last to encourage punctuality and keep the event within the timebox.
  • C Whoever the Developers choose to start.
  • D The person holding the talking stick.
Reveal correct answer

Correct answer: C

Explanation

The Daily Scrum is started by whoever the Developers decide should start. The Daily Scrum is an event for the Developers, and they are responsible for conducting it. The Scrum Master's role is to ensure that the event takes place and stays within the timebox, but it is up to the Developers to decide how to conduct the event.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need