Question 103
Who is responsible for setting the Definition of Done?
(choose the best answer)
-
A
The Scrum Team
- B The Scrum Master
- C The Product Owner
- D The Developers individually
Reveal correct answer
Correct answer: A
Explanation
If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product. The Developers are required to conform to the Definition of Done. If there are multiple Scrum Teams working together on a product, they must mutually define and comply with the same Definition of Done.