Question 102

Which statement is true about the duration of a Sprint?

(choose the best answer)

  • A The duration of a Sprint is determined during Sprint Planning and should be long enough to complete all planned work items
  • B The duration of a Sprint must be one month or less
  • C The duration of a Sprint should be adjusted based on the amount of work completed in previous Sprints
  • D The duration of a Sprint is determined during Sprint Planning and should include time for development and testing
Reveal correct answer

Correct answer: B

Explanation

According to the Scrum Guide, the heart of Scrum is a Sprint, which is a time-box of one month or less during which a "Done," usable, and potentially releasable product Increment is created. Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.