Project Management Professional PMP · Free Practice Question Easy
Question 97
Thomas is the project manager for Project Anchor, nearing completion with a CPI of .94 and an SPI of 1.01. Thomas has ensured that all tasks have been properly closed out and that deliverables have been delivered to customers. The vendors have provided the needed documentation, and the project sponsor is happy with the project result, though costs were slightly over budget. What else should Thomas do to close out Project Anchor?
- A Clear out the backlog.
- B Ensure all project contracts are closed out.
- C Finalize quality control.
- D Determine project velocity.
Reveal correct answer
Correct answer: B
Explanation
Thomas should review all project contracts to ensure they have been properly closed out and have met their terms. Closing all contracts must be completed before the project is officially closed, which can be coordinated with centralized contracting. However, Thomas may have to approve the invoices for payment as part of the organizational framework. Quality control happens before the customers see the result, so it is assumed that this task has been completed already. Given that all tasks have been closed out, there should not be a backlog. Predictive projects do not have a velocity.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.