Question 73

An organization has hired Ali to teach agile methodologies to a team of developers. She plans to use a website development project to teach the methods. As an agile coach, Ali's primary goal is to highlight value delivery to the team while reinforcing agile pillars and values throughout the process. Feedback loops are often inserted into sprints to ensure continuous learning throughout the development lifecycle. Whose role is it to ensure lessons learned are shared amongst the team, and during which ceremony?
  • A The entire team, during the daily standup meeting
  • B The entire team, during the project retrospective meeting
  • C The scrum master, during project retrospective meeting
  • D The entire team, during the sprint retrospective meeting
Reveal correct answer

Correct answer: D

Explanation

It is up to the entire team to ensure lessons learned are shared and incorporated throughout the project. The feedback mechanism is built into each sprint through the sprint retrospective meeting to improve on future sprints. In agile environments, the entire team, and not the scrum master, lead the project. Lessons learned are captured during the sprint retrospective meeting, not at the project retrospective meeting, to integrate the lessons learned in the next sprint.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need