Tia is the project manager for the Irvin Group, which subscribes to the agile approach to project management. Her development team is assessing the difficulty of requirements being completed in the current sprint. To figure out how many requirements can be completed in a sprint, which of the terms below describes the rating of the requirements?
- A Story points
- B Fist-to-five voting
- C Sprint backlog
- D Value analysis
Reveal correct answer
Correct answer: A
Explanation
The correct answer is story points. User stories are written requirements, and story points rank task difficulty in order to complete a user story in a sprint. The sprint backlog is not a process that rates requirements to determine how many requirements can be finished in a sprint and is therefore incorrect. Value analysis is not a process that rates requirements to determine how many requirements can be finished in a sprint and is therefore incorrect. Fist-to-five voting is not a process that rates requirements to determine how many requirements can be finished in a sprint and is therefore incorrect.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.