Question 65
Ben is a project manager at Blue Corporation, which is planning a new project. While speaking with stakeholders, Ben learns that the project scope is loosely defined and that Blue Corporation has not done this work in the past. What type of methodology is Ben likely to recommend?
- A Predictive
- B Agile
- C Hybrid
- D Cyclical
Reveal correct answer
Correct answer: B
Explanation
Given the project has a loosely defined scope, Ben is likely to recommend an agile approach. Predictive is not a good choice given the unfixed scope. While hybrid could be made to work, there is not enough information presented as to why hybrid would be the best answer presented. Cyclical is not a project management methodology.Discussion