You are a project manager for your organization. Your current project has a budget of $1,250,650 and is currently 75 percent done. Due to some errors by the project team, however, you were supposed to 80 percent as of today. In your project, you have spent $989,000. Management has asked for to report your Estimate to complete. What’s the best answer?
  • A ($68,017)
  • B 1.19
  • C $1,318,667
  • D $329,667
Reveal correct answer

Correct answer: D

Explanation

To calculate the estimate to complete (ETC), use the following formulas:

EV = .75 X 1,250,650 = $937,987.50

CPI = EV/AC = 937,987.50/989,000 = .94842

ETC = (BAC-EV)/CPI = (1,250,650 - 937,987.50)/.94842 = $329,667 (rounded)

The other answers are incorrect choices.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need