Question 41

Martina is the project manager of the Speedway Project. As she and the project team study the project management plan and its components, it becomes clear that the team does not understand why the project needs so much information. The difference between a project baseline and a project plan is what?
  • A Baselines only change at milestones, while project plans change as needed.
  • B A baseline is a snippet of the project plan, while project plans change as needed.
  • C A project baseline is a control tool, while project plans are tools for execution.
  • D Baselines and project plans are amended – they do not change.
Reveal correct answer

Correct answer: C

Explanation

The correct answer is that a project baseline is used as a control tool, while the project plan's execution and work results are measured against project baselines. A baseline is more than just a snippet of the project plan – it is the expectation of how the work should be done. Project baselines and project plans do change. Baselines can change along with the project plan.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need