Project Management Professional PMP · Free Practice Question Easy
Question 27
You are a project manager for the UYT Project, and you’re working with the project team to build out the project network diagram. You and the team are reviewing the relationships between several activities in the project, and you’re concerned about some of the soft logic the team has used for the activity relationships. Who determines the soft logic about activity relationships in a project?
- A Project team
- B Project lead
- C Project manager
- D Project sponsor
Reveal correct answer
Correct answer: A
Explanation
Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast-tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal. The project team determines which dependencies are discretionary during the process of sequencing the activities.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.