Question 149

Angela is a scrum master for her organization and she is working with the development team and the product owner to plan out the amount of work the team can take into the next sprint. The development team believes it can complete, as in previous sprints, 30 user story points. You quickly review the past iterations and see that the team has indeed, on average, completed 30 user story points per iteration. What term describes the 30 user stories per iteration for this team?
  • A Deliverables
  • B Velocity
  • C Kanban completion
  • D RAG Rating Green
Reveal correct answer

Correct answer: B

Explanation

Velocity is the term used to describe the stabilized amount of user story points a team can complete in a sprint. Deliverables is a generic project management term to describe the completed items the team has delivered as a result of the project work. Kanban completion is not a valid project management term. Kanban means signboard and is a way to pull work items from the waiting queue into production and through all phases of the project work to completion. RAG rating is a term to describe Red, Amber, and Green. It is often used as a quick visual way to identify issues, completed assignments, and other project management factors.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need