Project Management Professional PMP · Free Practice Question Easy
Question 122
Denise is a scrum master at Acme Corporation. Initial planning and high-level scoping have been completed for Project G. Denise would now like to acquire a team for this project. What should Denise do next?
- A Ask stakeholders to volunteer team members.
- B Ask people she worked with before to join the team.
- C Do nothing. Stakeholders will provide a team for her.
- D Analyze the initial plan and determine the skill sets needed.
Reveal correct answer
Correct answer: D
Explanation
Before Denise can acquire project resources, she needs to understand what competencies and skills are required for success. Once this is completed, she may begin finding a team. Without knowing what skills are needed, volunteers are not helpful. Asking people she has worked with before to join the team will not provide Denise with the necessary skills. Without more information, stakeholders cannot provide resources.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
