You are the project manager in your organization. Your project is part of a larger program led by Nan Gramble. Nan is a believer of McGregor's Theory of X and Y. Which of the following is an example of Theory X?
  • A Earned value management
  • B Micromanagement
  • C Self-led project teams
  • D Team members able to work on their own accord
Reveal correct answer

Correct answer: B

Explanation

Theory X states that workers have an inherent dislike of work and will avoid it if possible. Micromanagement is a method used to make certain workers complete their work and is part of Theory X. Self-led project teams are part of Theory Y and are a good component for a project team. Team members able to work on their own accord are self-directed teams and are part of Theory Y. EVM is not directly related to McGregor's Theory of X and Y.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need