Project Management Professional PMP · Free Practice Question Easy
Question 114
Jessica is the project manager for a project which has just officially begun and is scheduled to last fifteen weeks. The project has a budget of $100,000. Jessica would like to start planning a project schedule but is unsure if she has everything she needs. What is the project document displayed below, and does it help Jessica?

- A It is a milestone list, and it will let her build the schedule.
- B It is a list of activities and will help her build the schedule.
- C It is a list of project team members and will help her build a schedule.
- D It is a stakeholder register and will not help her with the schedule.
Reveal correct answer
Correct answer: B
Explanation
This is a list of activities, which will help Jessica begin planning a schedule. Without knowing what activities are needed, Jessica will be unable to acquire the right team. A milestone list would be an output of designing a schedule. A stakeholder register is used to track a project's stakeholders. The document displayed is not a list of project team members.Discussion