Project Management Professional PMP · Free Practice Question Easy

Question 111

What is represented in the provided image?


  • A Stakeholder engagement plan
  • B Stakeholder analysis
  • C Stakeholder engagement assessment matrix
  • D Stakeholder register
Reveal correct answer

Correct answer: C

Explanation

The image is a stakeholder engagement assessment matrix. It shows the current level of engagement and is used to create goals for better engagement in the project. A stakeholder analysis is a general activity that is performed; it is not a graph. An output of stakeholder analysis is a stakeholder engagement assessment matrix. A stakeholder engagement plan is a document that outlines why stakeholders need to be engaged and how they may be engaged; it is not represented graphically as the image provided is. A stakeholder register is a document that contains a list of stakeholders and information about them, typically in a list or similar fashion. The graphical representation provided here is a stakeholder engagement assessment matrix that compares stakeholder's current and desired engagement levels.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need