The customer has accepted your project but a stakeholder complains that the project did not increase the employees’ knowledge of Java programming and therefore, the project is not complete. You determine that all confirmed requirements have been met, and there is no evidence that Java programming was a requirement. A review of project correspondence shows no mention of the deliverable. You recommend that the project manager should:
- A Begin project closure.
- B Meet with the team to discuss the issue and find a resolution.
- C Get the project stakeholders involved to help resolve the issue.
- D Re-plan the project to include the new objective.
Reveal correct answer
Correct answer: A
Explanation
The full and satisfactory delivery of project deliverables marks the end of the work and the beginning of closure. The customer has accepted the project.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.