Question 24
In the facilitated workshop for a new inventory management system, There are conflicting views on whether some of the requirements identified are important. How can you BEST resolve this disagreement?
- A Capture all of the requirements, making certain that they are clearly understood.
- B Based on your knowledge of the solution, decide which requirements need to be included.
- C Estimate the cost of the requirements and then select the less expensive option.
- D Determine the requirements' perceived business value and whether any requirements are dependent on the others.
Reveal correct answer
Correct answer: D
Explanation
To prioritize requirements, analyze the perceived business value, look at dependencies, and facilitate consensus on what is to be included in the solution.Discussion