PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy
Question 49
A Kanban board is a great visual aid to assist in the review of:
- A The planning of work over the course of a release
- B The reasons for any bottlenecks in the current iteration
- C The priority and stage for work items in the current iteration
- D All items waiting in the backlog that need to be prioritized
Reveal correct answer
Correct answer: C
Explanation
The correct answer is the priority and stage for work items in the current iteration. A Kanban board is a visual representation of the work that needs to be done, what is currently being worked on, and what has been completed. It helps teams see the status of work at a glance and can be used in conjunction with Agile project management software.The other choices are incorrect. A Kanban board does not help the team visualize the backlog or a release, and it does not give the reason for a bottleneck.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.