Aaron has written a statement that briefly discusses in his charter what entity the project is for, their need, the product/service, and the product category. He is most likely writing:
  • A A project elevator statement
  • B A standard project charter
  • C An Agile approach statement
  • D A project planning statement
Reveal correct answer

Correct answer: A

Explanation

This is a description of a project elevator statement. An Agile project elevator statement is a brief and concise description of the project that can be communicated in the time it takes to ride an elevator, typically 30 seconds to a minute. It should communicate the purpose, benefits, and value of the project in a way that is easily understood by all stakeholders, including those who may not be familiar with the technical details. The statement should be clear and compelling and help align everyone's understanding of the project goals and objectives. The goal is to create a memorable and easily shareable summary that helps to build excitement and enthusiasm for the project.The other answers are not accurate names for this description. A standard project charter would not specifically include this. The project planning statement and Agile approach statement are fictional terms.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need