Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 43

As part of her weekly communications, Cecily sends out an email update of the project's status, including all of the current project information and any updates or changes to the project. The email communication is sent to all of the project's stakeholders. Cecily's weekly email is an example of which type of communication method?
  • A Pull communication
  • B Push communication
  • C Stakeholder management strategy
  • D Interactive communication
Reveal correct answer

Correct answer: B

Explanation

In this instance, Cecily is pushing the information to stakeholders. Push communication occurs when the sender pushes the information to the recipient. Pull communication occurs when the recipient must go to the source to get the communication. Interactive communication occurs when both sender and recipient engage in a mutual exchange of information. The stakeholder management strategy may guide some of your expectations, particularly those concerning stakeholder expectation management, but it is not a communication method. PCM10.4.120

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need