Certified Associate In Project Management CAPM · Free Practice Question Easy
Question 42
What is the main purpose of quality control in project management?
- A To improve customer satisfaction
- B To reduce project risks
- C To ensure conformance to project requirements
- D To increase project costs
Reveal correct answer
Correct answer: C
Explanation
The primary purpose of quality control in project management is to ensure that the project produces deliverables that meet the specified requirements and standards. This involves implementing processes and procedures to monitor and evaluate the quality of work throughout the project lifecycle, including identifying and correcting defects and non-conformances. By ensuring conformance to project requirements, quality control helps to ensure that the project is delivered on time, within budget, and to the satisfaction of all stakeholders, including the customer. PMFCC10Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.