Certified Associate In Project Management CAPM · Free Practice Question Medium

Question 32

You are the project manager for your organization. Your latest project has a BAC of $250,000. You have calculated your CPI to be .91 and your AC to $175,000. What is your project’s EAC?
  • A $25,000
  • B $15,750
  • C $265,000
  • D $275,000
Reveal correct answer

Correct answer: D

Explanation

The formula EAC = BAC / CPI is written, in this instance, as EAC = 250,000 / .91. This equates to $274,725, which is rounded up to $275,000. 1, 2, and 3 are all incorrect because these are erroneous calculations.