Certified Associate In Project Management CAPM · Free Practice Question Medium
Question 32
You are the project manager for your organization. Your latest project has a BAC of $250,000. You have calculated your CPI to be .91 and your AC to $175,000. What is your project’s EAC?
- A $25,000
- B $15,750
- C $265,000
- D $275,000
Reveal correct answer
Correct answer: D
Explanation
The formula EAC = BAC / CPI is written, in this instance, as EAC = 250,000 / .91. This equates to $274,725, which is rounded up to $275,000. 1, 2, and 3 are all incorrect because these are erroneous calculations.Discussion