Question 31
What is the main purpose of a Sprint burndown chart in Agile project management?
- A To visualize the progress of the entire project
- B To measure the amount of work remaining in the Sprint
- C To track the progress of individual team members
- D To measure the velocity of the team
Reveal correct answer
Correct answer: B
Explanation
To measure the amount of work remaining in the Sprint. A Sprint burndown chart is used in Agile project management to visualize the amount of work remaining in a Sprint. It shows the amount of work that has been completed and the remaining work over time. The chart helps the team to track their progress and identify any potential roadblocks early on, allowing them to take corrective action before it's too late. AFM67Discussion