Prince2 7 Foundation · Free Practice Question Easy
Question 33
What is an advantage of applying the manage by exception principle?
- A It allows the project team to delegate the authority for day-to-day control of a project to the project manager
- B It allows the project board to delegate cost tolerances to the project manager
- C It allows the project team to fully understand their roles and responsibilities
- D It allows the project team to identify improvements to be made during the project
Reveal correct answer
Correct answer: B
Explanation
OBJ 2.1: A PRINCE2 project has defined tolerances for each project objective to establish limits of delegated authority. This is an advantage of applying the manage by exception principle.Discussion