Prince2 7 Foundation · Free Practice Question Medium
Question 32
According to the manage by exception principle, what should be defined to establish limits of delegated authority?
- A Scope
- B Costs
- C Timescales
- D Tolerances
Reveal correct answer
Correct answer: D
Explanation
OBJ 2.1: A PRINCE2 project has defined tolerances for each project objective to establish limits of delegated authority. PRINCE2 enables appropriate governance by defining distinct responsibilities for directing, managing and delivering the project and clearly defining accountability at each level. These tolerances are set against the six aspects of performance (costs, time, quality, scope, benefits, and risks).Discussion