LEED AP Building Design Construction LEED AP BDC · Free Practice Question Medium

Question 34

Project designer is having difficultly with the design as the there is no access to haulers or external facilities for waste collection area in the design. What can he do to fix the situation?

  • A

    Establish accessible recycling areas for occupants and users.

  • B

    Replace the prerequisite with another pilot prerequisite that meets the same intent.

  • C

    Report the case to GBCI and seek alternative route for certification.

  • D

    Eternal facilities and haulers.

Reveal correct answer

Correct answer: A

Explanation

Projects where there is no access to haulers or external facilities must still comply with this prerequisite by establishing accessible recycling areas. As an interim measure, until a recycling service becomes available, consider alternative means of recycling, such as reuse or donation. Reference: LEED BD+C Reference guide - page: 529

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.