Question 21
Who is responsible for implementing erosion and sedimentation control (ESC)?
-
A
3rd Party Agent
-
B
Civil Engineer
-
C
Architect
-
D
Mechanical Engineer
Reveal correct answer
Correct answer: B
Explanation
The civil engineer is typically responsible for developing an erosion and sedimentation control (ESC) plan, but in some cases, the landscape architect, project hydrologist, geologist, earthworks contractor, or general contractor will undertake the plan’s development. Reference: LEED BD+C Reference Guide - Page 185Discussion