LEED AP Building Design Construction LEED AP BDC · Free Practice Question Easy
Question 17
Project team wants to target LEED Gold certification for a healthcare project. One of the requirements is to provide permenant water meters. To achieve WE Prerequisite Building-Level Water Metering, what should be metered?
-
A
Total potable and non-potable water use
-
B
Total potable water use
-
C
Total Non-potable water use
-
D
Alternative water use and process water
Reveal correct answer
Correct answer: B
Explanation
The WE Prerequisite Building-Level Water Metering requires Installing permanent water meters that measure the total potable water use for the building and associated grounds. Reference: LEED BD+C Reference guide - page: 283Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.