Entry Certificate In Business Analysis ECBA · Free Practice Question Medium
Question 2
Halfway through the project, it’s clear that the solution being built no longer meets the evolving business needs. What should you do?
-
A
Continue with the current build since work is already underway
-
B
Analyze how business realities have shifted, assess the impact, and recommend adjustments
-
C
Pause development and request an urgent re-planning session
-
D
Document the discrepancy and suggest handling it after delivery
Reveal correct answer
Correct answer: B
A.
Staying the course may save effort but delivers limited value.
B.
Analyzing shifts and adjusting keeps the solution aligned to business needs.
C.
Stopping work outright may overreact before impact is properly assessed.
D.
Deferring the issue risks wasted investment and poor adoption.
Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.