Certified Business Analysis Professional CBAP · Free Practice Question Medium

Question 15

After reviewing the project backlog of requirements, you realize there are gaps in it: chunks of requirements are missing. Which activity, if performed correctly, would have helped prevent this?

  • A Prioritize requirements
  • B Allocate requirements
  • C Plan business analysis information management
  • D Define requirements architecture
Reveal correct answer

Correct answer: D

Explanation

An architecture helps ensure that a set of requirements is complete. BABOK 7.4 Define Requirements Architecture