Istqb Certified Tester Foundation Level CTFL · Free Practice Question Easy
Question 56
Which of the following is NOT a work product of test implementation?
-
A
Test procedures
-
B
Test suites
-
C
Test execution schedule
-
D
Change requests
Reveal correct answer
Correct answer: D
A.
Test procedures are a work product of test implementation, as they outline the specific steps and processes to be followed during testing.
B.
Test suites are collections of test cases that are grouped together for execution. They are created during the test implementation phase and are considered a work product.
C.
The test execution schedule outlines when tests will be run and is classified as a work product of test implementation.
D.
Change requests are not a work product of test implementation; they are generated as part of test completion work products. They typically arise from lessons learned or actions needed to improve future projects or iterations.