Istqb Certified Tester Foundation Level CTFL · Free Practice Question Medium

Question 55

A team uses three-point estimation with measurement error to estimate the test effort needed for a new feature. An expert team came up with the following estimates:

• most optimistic estimation: 6 person-hours

• most likely estimation: 12 person-hours

• most pessimistic estimation: 18 person-hours

What is the final estimate?

  • A

    between 9 and 11 person-hours

  • B

    between 11 and 13 person-hours

  • C

    between 10 and 14 person-hours

  • D

    between 13 and 15 person-hours

Reveal correct answer

Correct answer: C