SAFE Scrum Master Ssm · Free Practice Question Easy
Question 18
What is considered an anti-pattern for the Iteration Retrospective ?
-
A
Discussing Iteration metrics during the retrospective.
-
B
Choosing an action item for another Team.
-
C
Focusing on what to preserve as well as what to improve.
-
D
Adding improvement items to the Team Backlog.
Reveal correct answer
Correct answer: B
Explanation
Choosing an action item for another Team is not an expected activity performed in iteration retrospectives.
Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.