SAFE Scrum Master Ssm · Free Practice Question Easy

Question 18

What is considered an anti-pattern for the Iteration Retrospective ?     

  • A

    Discussing Iteration metrics during the retrospective.   

  • B

    Choosing an action item for another Team.   

  • C

    Focusing on what to preserve as well as what to improve.   

  • D

    Adding improvement items to the Team Backlog.   

Reveal correct answer

Correct answer: B

Explanation

Choosing an action item for another Team is not an expected activity performed in iteration retrospectives.


Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need