Question 17

What are two outputs of the PI Planning ?     

  • A

    Team Backlog and Top 10 Features.     

  • B

    ART Planning Board and Team Backlog.   

  • C

    ART Planning Board and ART PI Objectives.     

  • D

    Porfolio Backlog and Team Backlog.     

Reveal correct answer

Correct answer: C

Explanation

A successful PI Planning Event delivers two primary outputs:

  • Committed PI objectives: A set of SMART objectives that are created by each team with the business value assigned by the Business Owners;

  • ART Planning Board: Highlighting the new feature delivery dates, feature dependencies among teams and relevant Milestones.