SAFE Scrum Master Ssm · Free Practice Question Medium
Question 2
What are common PI Planning anti-patterns ?
-
A
The team decides which changes need to happen and when.
-
B
Too much time is spent prioritizing Features.
-
C
Stories are created for the Iterations.
-
D
Too much time is spent analyzing each Story and Scrum Masters who work with multiple teams do not have time for their teams.
Reveal correct answer
Correct answer: D
Explanation
Scrum Master should be able to spend enough time with their own teams during PI planning and Teams should not take too much time analyzing each User Story.
Discussion