Question 1

What is considered an anti-pattern for the Iteration Retrospective?
  • A Adding improvement items to the Team Backlog
  • B Choosing an action item for another Team
  • C Discussing Iteration metrics during the retrospective
  • D Focusing on what to preserve as well as what to improve
Reveal correct answer

Correct answer: B

Explanation

Choosing an action item for another Team is not an expected activity performed in iteration retrospectives.