LEED AP Building Design Construction LEED AP BDC · Free Practice Question Easy
Question 40
A Project Credit Interpretation Ruling (CIR) process is designed to allow Project Teams to obtain technical guidance. Which of the following statements in true about CIRs?
-
A
A CIR is submitted by LEED administrator only.
-
B
A CIR access is available to third party testing agency.
-
C
A CIR is submitted during design phase only
-
D
A CIR can be submitted for credits and prerequisites.
Reveal correct answer
Correct answer: D
Explanation
A CIR can be submitted by any team member during any phase of the project. Third party testing agency usually doesn't have any access to CIRs unless they were given an exception and access by project team.CIR can be submitted for credits and/or prerequisites.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.