Professional Scrum With Kanban PSK I · Free Practice Question Easy

Question 3

What is the Work Item Age and Workflow Stage of the Work Item where the blue arrow is pointing?


  • A

    Work Item Age: 2

    Stage: Code Review

  • B

    Work Item Age: 2

    Stage: In Progress

  • C

    Work Item Age: 5

    Stage: In Progress

  • D

    Work Item Age: 5

    Stage: Analysis

Reveal correct answer

Correct answer: C

Explanation

If you draw a horizontal and vertical line from a Work Item you can see that the Work Item Age (represented on the left axis) is 5 and the Stage is 'In Progress' as shown on the horizontal axis.