PMI Professional In Business Analysis PMI Pba · Free Practice Question Medium
Question 42
You will be eliciting requirements from employees in your company and third party resources from a vendor. During your planning, you ask for an initial list of risks, meeting availability, and business operational constraints, These will help you to:
- A Develop strategies for sequencing elicitation activities.
- B Decide which stakeholders will contribute which types of requirements.
- C Choose the appropriate elicitation techniques.
- D Design the requirements documentation format and formality.
Reveal correct answer
Correct answer: A
Explanation
Sequencing elicitation activities depends on knowing where the business value is to be gained, risks, stakeholder availability, and business constraints such as seasonal constraints, plant shutdowns, etc.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
