Question 24

In the facilitated workshop for a new inventory management system, There are conflicting views on whether some of the requirements identified are important. How can you BEST resolve this disagreement?
  • A Capture all of the requirements, making certain that they are clearly understood.
  • B Based on your knowledge of the solution, decide which requirements need to be included.
  • C Estimate the cost of the requirements and then select the less expensive option.
  • D Determine the requirements' perceived business value and whether any requirements are dependent on the others.
Reveal correct answer

Correct answer: D

Explanation

To prioritize requirements, analyze the perceived business value, look at dependencies, and facilitate consensus on what is to be included in the solution.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need